
The demolition of a building usually requires either a permit or a notification submitted to Building Control Services.
Demolition permit
As a general rule, the demolition of a building requires a demolition permit.
However, a demolition permit is not required if:
- demolition is required under a valid building permit
- demolition is required under an approved street plan, road plan or railway plan.
Demolition notification
If the building is an accessory building or another minor structure that is not considered historically or architecturally valuable nor part of such a complex, a written demolition notification must be submitted to the Building Control Services at least 30 days before demolition work begins.
During this period, the Building Control Services may, for justified reasons, require an application for a demolition permit to be submitted.