Inspections related to building work ensure that the work proceeds in accordance with the permit decision and that requirements are met at different stages.
Inspections and checks related to the building permit must be carried out during the validity of the permit. The permit decision specifies which inspections are required for the project.
Before construction work begins, a commencement notice must be submitted or an pre-construction meeting arranged. All construction work requiring a permit must also undergo a final inspection.
Inspection process
Below is a typical sequence of inspections. Always check the exact requirements in your permit decision.
- Before building work begins
- Commencement notice or pre-construction meeting
- Building site and foundations
- Building location marking
- Location inspection
- Geothermal borehole location inspection
- During construction
- Structural inspection
- HVAC inspections (heating, ventilation and air conditioning)
- Final stage of building work
- Commissioning inspection (partial final inspection)
- Final inspection.
Requesting inspections
Commencement notice
Requesting meetings and inspections
- Pre-construction meeting
- Structural inspection
- Commissioning inspection
- Final inspection
-
-
-
Hintsala Juha-Pekka
Inspection Engineer, Building Control
Requesting HVAC inspections
Inspections requested through the City of Vaasa surveying services
- Building location marking
- Location inspection
- Geothermal borehole location inspection
NB! Inspections carried out by the Surveying Services Department are invoiced separately in accordance with its current price list.
Related documents and instructions
An operation and maintenance manual must be prepared for a new building; it must be sufficiently complete at the latest when applying for the final inspection so that it can be handed over to the building owner.
In addition to new construction, the obligation to provide an operation and maintenance manual also applies to repair and alteration works that are comparable in scope to new construction, and, where applicable, to other permit-required repairs.
The manual contains information based on the building’s purpose and characteristics needed for its proper use and maintenance. It presents, among other things, the intended service life of building parts and equipment and instructions for maintenance measures.
During construction, the persons responsible and the inspectors of the different work phases record and confirm their inspections in the construction inspection document.
The document also records any substantiated remarks related to deviations of the construction work from regulations or plans. Entries may be made, for example, by the client, designer, contractor or other expert.
A note is made in the final inspection minutes regarding the maintenance of the inspection document, and its summary is archived together with the building’s permit documents.
Below you can find the forms related to inspection documents.
- Construction work inspection document (pdf in Finnish and Swedish)
- Inspection document for geothermal heating (pdf in Finnish and Swedish)
- Chimney and fireplace inspection report (pdf in Finnish and Swedish)
- Summary form for water and sewer systems inspection document (pdf in Finnish and Swedish)
- Summary form for ventilation systems inspection document (pdf in Finnish and Swedish)
- Before the building is commissioned, the person who prepared the energy assessment must validate the energy certificate included in the assessment.
- Finlex – Act on the energy performance certificate of buildings (50/2013) (in Finnish and Swedish)