Winter maintenance includes removal of snow and ice, anti-slip measures and sand removal. We also remove snow banks and keep street ditches and stormwater gutters free of snow and ice.
When are the pedestrian and bicycle paths ploughed?
Pedestrian and bicycle paths are cleared in the order of maintenance classes. The busiest routes are treated first.
Snow ploughing:
- Daytime 05:00–23:00: we start no later than when 2 cm of snow has fallen.
- Night 23:00–05:00: we start no later than when 3 cm of snow has fallen.
Slush removal:
- Daytime 05:00–23:00: we start no later than when slush is at least 2 cm.
- Night 23:00–05:00: we start no later than when slush is at least 3 cm.
We start no later than when 3 cm of snow has fallen or when there is 2 cm of slush.
We start no later than when 5 cm of snow has fallen or when there is 4 cm of slush.
When are streets and roadways ploughed?
Streets are ploughed according to maintenance classes. Main streets and public transport routes are treated before smaller streets.
We start no later than when 3 cm of snow has fallen or when there is 3 cm of slush.
We start no later than when 6 cm of snow has fallen or when there is 5 cm of slush.
We start no later than when 6 cm of snow has fallen or when there is 5 cm of slush.
Winter maintenance emergency duty 16:00–07:00
In urgent situations and those that endanger safety, you can call the Public Utility Services duty number 040 137 1913 outside office hours at 16:00–07:00.
The duty operates during the winter maintenance season from 15 October to 15 April.
If your matter is not urgent, please leave your feedback via the feedback service.