The aim is to develop the area into a high-quality urban milieu as part of the park and leisure zone surrounding the city waterfront. The development of the area is awaiting the completion of the master plan.
Progress of the planning process
1
Initiation
26.11.2013
2
Participation and assessment plan
26.11.-20.12.2013
3
Draft
10.3.-15.4.2015
4
Proposal
5
Approval
The local detailed plan has not been approved.
6
In force
The local detailed plan is not legally valid.
Preparer
-
Schulte-Tigges Oliver
Planning Architect, Urban planning