The detailed plan for the traffic arrangements of Yhdystie and the motorway is legally valid. The plan project relates to the development of Yhdystie into a four-lane main road.
With the implementation of the plan, long-distance traffic will be directed to the main roads, which will reduce through-traffic on residential streets. The construction of a second carriageway and, in particular, converting junctions into grade-separated solutions will significantly improve traffic flow, especially during peak hours. The plan also examined the placement of commercial and office buildings along Yhdystie.
The planning materials are available in Finnish and Swedish.
Progress of the planning process
1
Initiation
17.02.2015
2
Participation and assessment plan
01.-15.10.2015
3
Draft plan
01.-15.10.2015
4
Plan proposal
08.09.-10.09.2016
5
Approval
Approved by the City Council on 04.05.2020.
6
Administrative Court
21.03.2022
An appeal against the detailed plan was filed with the Administrative Court of Vaasa on 15.06.2020.
7
Supreme Administrative Court
01.12.2022
8