Partial master plan for Merkkikallio

The partial master planning for the Merkkikallio wind farm began in 2014 in cooperation with the municipality of Mustasaari.

The partial master plan was approved by the municipal councils in early 2017. The plan enables the construction of three wind turbines in the Vähäkyrö area of Vaasa.

Progress of the planning process

1

Initiation 16.4.2015

2

Draft 2.6.-2.7.2015

3

Proposal 12.1.-12.2.2016

4

In effect 30.4.2021